Hello important news for those involved and working in the field of photovoltaics, it was announced the new Decree on the Energy Bill 2011/2013, which will come into force on 1 January 2011 .
The highly anticipated new decree on the Energy Bill 2011/2013, which will come into force on 1 January 2011, was finally published (Decree 6 Aug. 2010, OJ 24 August 2010, No. 197) . In a summary in several important respects.
Remember that what is supposed to be written in a note. And as such this post is not going to change the decree, therefore, every argument must be treated always satisfied with the official decree published by OJ August 24, 2010, No. 197.
The first important difference from the previous decree is the transition from three to six classes of the power mechanism, but also the elimination of the type of "partially integrated system" (which had created various problems in evaluation of incentive rate in relation to the choice of "plant Integrated ") to have only two types of system: systems installed on buildings and plants on land (or other plants).
Table A shows the rates that will apply from 1 January 2011, as you can see the same suffering a cut in their first year in three different periods. This close temporal regression in 2011 could create difficulties for plants for proper assessment of the economic viability of a plant.
In practice you may encounter cases where plants whose budgets have been prepared in a quarter are then applied and consequently networked in the next, and thereby lowers the incentive rate and change in the economic recovery plan.
In subsequent years, 2012 and 2013, however, the rates of 2011 presented in Table A, column C, will undergo a fixed reduction of 6% per year.
The order provides specific incentives for integrated systems with innovative features. We intend to photovoltaic modules and components that use special architectural features developed specifically to replace. Table B shows the relative rates. They are also considered to be specific about the increases in tariffs.
Among the awards considered:
• 5% for systems installed on buildings in areas classified as industrial, commercial, quarries and landfills, and those operating under the net metering placed on buildings made by municipalities with a population less than 5,000 inhabitants, of which such municipalities are responsible parties;
• 10% more for equipment installed in replacement of asbestos roofing or otherwise containing asbestos;
• 20% increase due in each day that a plant is part of a system with predictable exchange profile. This is a new concept introduced by the decree. Means a system which meets all of the following characteristics:
or consists of one or more photovoltaic systems managed by the person responsible for a unit with an aggregate of points of entry, sampling points and any of the storage systems' energy, and treated on an hourly basis to a single underlying primary substation;
or is made with one or more photovoltaic systems that have a total rated power exceeding 200 kW but less than 10 MW. This power nominale deve inoltre essere almeno pari alla somma delle potenze nominali degli eventuali impianti di produzione diversi dagli impianti fotovoltaici, nonchè alla somma delle potenze disponibili dei punti di prelievo di cui al punto precedente;
o ha un profilo complessivo di scambio con la rete elettrica che rispetta un programma orario nelle ore comprese tra le 8.00 e le 20.00, comunicato il giorno prima dal soggetto responsabile al soggetto responsabile con un margine di errore del 10% in ciascun giorno;
o il profilo di cui sopra è rispettato per almeno 300 giorni all’anno
• Finally, you can get a maximum increase of 30%, half the percentage improvement achieved by the reduction of energy requirements, if they are effectual work to improve the energy performance of a building.
The photovoltaic modules which are structural components of the arbors, solar greenhouses (which are eligible for fees only if agricultural activities are conducted throughout the period on the acceleration), sound barriers, shelters and canopies will also be entitled to a fee equal to the average between the price achieved for photovoltaic systems on buildings and the rate for 'other photovoltaic installations.
we consider plants with those on the ground to form a height less than 2 feet above the ground at the lowest point. All tracking systems are considered assemblies.
As regards the cumulation of the incentives the decree provides that the tariffs be combined only with the following benefits and government grants intended to implement the system:
a) grants capital by not more than 30% of the cost of investment made on buildings with photovoltaic perimpianti rated not more than 3kW;
b) capital grants of up to 60% of investment cost for photovoltaic systems that are made to public schools or any type and level playing field and that the person responsible for both the school or the subject the owner of the school, as well as public health facilities, or at the administrative headquarters buildings that are owned by local or autonomous regions and provinces;
c) capital grants for no more than 30% of investment cost for photovoltaic systems that are made to public buildings owned by organizations recognized non-profit social ensure that the provision of social services entrusted to local authorities, and that the person responsible for both the public body or organization non-profit social
d) capital contributions to an extent not exceeding 30% of investment cost for photovoltaic systems
by areas subject to remediation, are within the contaminated sites, provided the person responsible for the plant bears the direct responsibility of preventive remediation;
s) capital grants for no more than 30% of investment cost for photovoltaic systems integrated with innovative features;
f) capital contributions to an extent not exceeding 30% of investment cost for photovoltaic concentration;
g) soft loans granted pursuant to Article 1 paragraph 1111, the Law of 27 December 2006, no 296;
Another novelty introduced by the decree is that the GSE will and will provide the incentive rate payable within one hundred twenty days from the date of receipt of the request (the current time is much longer), and for reducing the time procedures, submitting the documentation required will be Only on the internet.
This will be prepared and made operational on the portal GSE a platform for communication between the responsible actors and the project supervisor. Finally, the new decree provides for the objectives and limits the cumulative electrical power.
The national target of nominal power accumulated by photovoltaic installation was established in 8000 MW by 2020 (this figure is considered to be greatly underestimated by all operators).
The availability of cumulative electric power of PV systems eligible for the incentive rates of this decree is established in 3000 MW, the PV system integrated with innovative features in 300 MW and, finally, that relating to photovoltaic concentration of 200 MW.
The GSE will publish on its website and continuously update the cumulative value of the power plant came into operation and, if the equipment is available, will be entitled to the incentive rates in plants that begin operation within fourteen months (twenty-four months for installations where only responsible parties are public entities) from the dates notified by the GSE on its website, which results in the roofs of availability above.
soon